Guide Running the program · 7 min read

What response targets should you set by priority?

The short answer

  • An automatic reply is not a response, and one number hides that.
  • Six clocks sit between the request and the closeout, each with its own owner.
  • Define what a priority means before you attach a time to it.
  • Fill the target table from your own work order history.
ONE WORD, SIX CLOCKS responded Request in Reviewed Dispatched Arrived Made safe Back in use Closed what the site actually waited
Facility work order response clocks from request to closeout. One reply time answers for the orange span only.

A maintenance request can receive an automatic reply in seconds and still sit untouched for the rest of the day. The system records a response, while the location sees that nobody has taken action.

The confusion starts when every step is rolled into one number called "response time." A useful service-level plan separates the handoffs, assigns an owner to each one, and makes it clear which promise the location is actually receiving.

Response is not one clock

Track six points between the first request and the final closeout.

Swipe to see the whole table

ClockWhat it measuresWhat stops the clockTypical owner
Human reviewTime from submission until someone reviews the risk, confirms the priority, and identifies missing informationThe request has been reviewed by a personFacilities coordinator
Service provider acceptanceTime from dispatch until a provider agrees to take the workThe provider accepts the jobDispatcher or service manager
ArrivalTime from acceptance until the technician reaches the locationThe technician checks in on siteService provider
Risk containmentTime until active damage or immediate risk is under controlWater is stopped, power is isolated, or the site is securedTechnician and facilities lead
Service restorationTime until the affected area, asset, or operation can be used againNormal use returns, even if follow-up work remainsService provider
CloseoutTime until the notes, photos, final scope, invoice, and follow-up work are recordedThe completed record passes reviewService provider and facilities coordinator

These clocks answer different questions. A fast human review does not guarantee a fast arrival, and an arrival does not mean the problem was fixed. Reporting them separately shows where the delay actually occurred.

Define each priority before assigning a time

Priority should reflect visible risk and operational impact. It should not depend on which location manager is the most persistent.

Swipe to see the whole table

PriorityPlain-language meaningTypical conditions
P1: EmergencySomeone could be harmed, major damage is actively spreading, the location cannot be secured, or the location cannot operate safelySmoke or sparks, uncontrolled water near electrical equipment, a serious life-safety issue, or an entrance that cannot be secured
P2: UrgentThe issue is seriously affecting operations or is likely to get worse, but there is no immediate threat to life or major property lossRefrigeration temperature is rising, a major area is unusable, or a critical asset is down without a practical workaround
P3: RoutineThe impact is limited, the condition is stable, and the location has a reasonable workaroundA single fixture is out, a noncritical door is difficult to use, or cosmetic damage needs repair

When there is a real emergency, the location should contact 911, the fire department, police, or the utility first. A work order does not replace emergency services.

What times should go in the target table?

There is no responsible universal answer for arrival or completion. A plumbing network in Miami, an elevator provider in a small market, and a refrigeration call at midnight will not perform on the same timeline.

Build the table in two parts:

  1. Set the internal targets.Human review, dispatch, escalation, and updates are controlled by your own process. Keep those expectations consistent across the portfolio.
  2. Set the field targets.Acceptance, arrival, containment, and restoration should reflect the trade, market, site hours, and after-hours coverage.

Use a table like this for each priority:

Swipe to see the whole table

TargetP1P2P3
Human reviewWithin ___ minutes, 24/7Within ___ minutes during coverage hoursWithin ___ business hours
Provider acceptanceWithin ___ minutesWithin ___ hoursBy ___
ArrivalBy trade and marketBy trade and marketScheduled date
Status updatesEvery ___ minutes until containedAt each status change or every ___ hoursWhen the schedule changes
Risk containmentAs soon as the hazard can be controlled safelyDefined by issue typeUsually not applicable
Service restorationTarget by trade and conditionTarget by trade and conditionScheduled completion
CloseoutWithin ___ hours after workWithin ___ hours after workWithin ___ business day(s)

Fill the blanks from actual work-order history. Use the median to understand normal performance and the 90th percentile to see what locations experience when a job runs long. A target built only around the average will hide the difficult calls.

Public organizations offer useful examples of how priorities can be defined, but their times should not be copied into a private facility program. Pasco County publishes separate definitions and targets for its own facilities. The useful lesson is the structure: define the condition and the expected response together, then set the timing around the operation and service network you actually have.

Keep the meaning consistent when the market changes

A P1 should mean the same thing at every location. What may change is how long a specific trade needs to arrive.

If a remote market has limited overnight coverage, write that reality into the arrival target and escalation plan. Do not weaken the definition of P1 to make the report look better. The risk is still an emergency even when the nearest qualified technician is farther away.

Before publishing a target, test it against:

  • Actual arrival history by trade and market
  • Normal and after-hours performance
  • Travel time and site-access restrictions
  • Parts or equipment that require specialty support
  • The availability of a qualified backup provider

An honest target gives the location something it can plan around. An unrealistic promise creates more calls and less trust.

Write the after-hours plan separately

Most response tables are built around normal business hours, but the plan is tested at night, on weekends, and during holidays.

The after-hours section should state:

  • Who reviews and confirms a P1
  • Which number the location should call
  • Which providers have verified live-answer coverage
  • When the backup provider or manager is contacted
  • What the location should do while help is on the way
  • How often the location will receive an update

Test the call list. A number in a spreadsheet is not coverage until someone confirms that it reaches the right person after hours.

Allow priority changes, but record them

A priority may need to move up or down when new information arrives. Record who changed it, when it changed, and why.

Review those changes monthly. Frequent upgrades from P3 to P2 may mean routine work is sitting too long. Frequent downgrades after arrival may mean the request form is missing the questions needed to judge the impact correctly.

The change itself is not the problem. Unexplained changes are.

Pause only the clock that is truly blocked

Some events justify a pause:

  • The location cannot provide access
  • Work cannot continue safely
  • Required approval is still pending
  • A required part is on order
  • The customer has asked for work to be held

Record the reason, the person responsible for the next step, and the next update date. A parts delay may pause the restoration target, but it should not erase the original arrival time. Each clock should preserve what actually happened.

Escalate before the miss

Set escalation points before a live job needs them. At minimum, name:

  1. The facilities coordinator handling the request
  2. The manager who can remove an internal block
  3. The person who can activate a backup service provider
  4. The location contact who needs the update

The fourth name is easy to overlook. The location may not be able to speed up the repair, but it still needs enough information to protect customers, employees, inventory, and the day's operation.

Review the whole path

Do not reward a fast acknowledgement while ignoring a slow repair. Review:

  • Percentage of requests reviewed within target
  • Percentage accepted and arrived within target
  • Time to contain risk
  • Time to restore normal use
  • Percentage completed on the first visit
  • Priority changes and the reasons behind them
  • Closeout time and documentation quality

First-visit completion deserves special attention. When the right technician arrives with the right information and parts, arrival, restoration, cost, and customer experience usually improve together.

Pebble keeps each timestamp, owner, update, and priority change on the same work order. That makes it possible to see whether delay is happening during review, dispatch, travel, repair, or closeout instead of treating the entire job as one response-time number.

ReferencePasco County Facilities Management service level agreement.

Bedrock Facility Solutions

Bedrock Facility Solutions manages facility programs for multi-location operators across the United States.

Published 4 August 2026. Last reviewed 25 August 2026.

Where is response time being lost?

A facility assessment maps each handoff in the current process and shows where requests are waiting, where ownership is unclear, and which targets the service network can realistically support.